Original Cost
₹862 Cr
Baseline estimate
Revised Cost
₹618 Cr
Latest approved cost
Expenditure
₹210 Cr
Spent to date
Utilization
34.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹407 Cr
Budget left
Spent
₹210 Cr
Remaining
₹407 Cr
Total
₹618 Cr
Project Approved
Construction / Implementation
Original End Date
29/04/2027
Revised Completion
29/04/2027
Completed
Project is within original budget of ₹862 Cr — no cost escalation recorded.
Expenditure stands at ₹210 Cr, which is 34.1% of the revised project cost.
Remaining budget: ₹407 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.