Roads & HighwaysIPM · Central Project#618093

Up-gradation to 2 lane with Paved shoulder from Charbhuja at Design km 0.00 existing km 150.00 to Neechli Oden Nathdwara at Design ch. Km 88.800 existing km 55.950 of NH-162E on EPC mode.

Ministry of Road Transport & HighwaysRajasthan
Revised Cost: ₹838 CrUtilization: 6.6%

Original Cost

₹838 Cr

Baseline estimate

On budget

Revised Cost

₹838 Cr

Latest approved cost

Expenditure

₹55 Cr

Spent to date

Utilization

6.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹783 Cr

Budget left

Budget Utilization

6.6%
0%25%50%75%100%

Spent

₹55 Cr

Remaining

₹783 Cr

Total

₹838 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/09/2025

Revised Completion

Completed

Project Details

Project Code618093
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateRajasthan
Data Month2026-05

Financial Summary

Original Cost₹838 Cr
Revised Cost₹838 Cr
Expenditure₹55 Cr
Original End Date26/09/2025
Revised DateN/A

Project Intelligence

Project is within original budget of ₹838 Cr — no cost escalation recorded.

Expenditure stands at ₹55 Cr, which is 6.6% of the revised project cost.

Remaining budget: ₹783 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Up-gradation to 2 lane with Paved shoulder from Charbhuja at Design km 0.00 existing km 150.00 to Neechli Oden Nathdwara at Design ch. Km 88.800 existing km 55.950 of NH-162E on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹838.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Up-gradation to 2 lane with Paved shoulder from Charbhuja at Design km 0.00 exis"?
Up-gradation to 2 lane with Paved shoulder from Charbhuja at Design km 0.00 existing km 150.00 to Neechli Oden Nathdwara at Design ch. Km 88.800 existing km 55.950 of NH-162E on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Rajasthan. Original cost: ₹838 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹838 Cr has not been significantly revised. Expenditure: ₹55 Cr (6.6% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Up-gradation to 2 lane with Paved shoulder from Charbhuja at is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618093. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Up-gradation to 2 lane with Paved shoulder from Charbhuja at is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.