Roads & HighwaysIPM · Central Project +26.1% overrun#619166

Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹968 CrUtilization: 52.6%Overrun: +₹200 Cr

Original Cost

₹768 Cr

Baseline estimate

+26% overrun

Revised Cost

₹968 Cr

Latest approved cost

Expenditure

₹509 Cr

Spent to date

Utilization

52.6%

Of revised budget

Escalated

Cost Status

+26.1%

+₹200 Cr increase

Remaining

₹459 Cr

Budget left

Budget Utilization

52.6%
0%25%50%75%100%

Spent

₹509 Cr

Remaining

₹459 Cr

Total

₹968 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹768 Cr

Revised Cost

₹968 Cr

Increase

+₹200 Cr

Escalation

+26.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/12/2025

Revised Completion

30/09/2026

Completed

Project Details

Project Code619166
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹768 Cr
Revised Cost₹968 Cr
Expenditure₹509 Cr
Original End Date14/12/2025
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹200 Cr (26.1%) from the original estimate of ₹768 Cr.

Expenditure stands at ₹509 Cr, which is 52.6% of the revised project cost.

Remaining budget: ₹459 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹768.00 Cr, later revised to ₹968.42 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi"?
Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹768 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹768 Cr and has been revised to ₹968 Cr — a cost overrun of +26.1%. Expenditure to date: ₹509 Cr (52.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619166. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.