Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi
Original Cost
₹768 Cr
Baseline estimate
Revised Cost
₹968 Cr
Latest approved cost
Expenditure
₹509 Cr
Spent to date
Utilization
52.6%
Of revised budget
Cost Status
+26.1%
+₹200 Cr increase
Remaining
₹459 Cr
Budget left
Budget Utilization
52.6%Spent
₹509 Cr
Remaining
₹459 Cr
Total
₹968 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹768 Cr
Revised Cost
₹968 Cr
Increase
+₹200 Cr
Escalation
+26.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
14/12/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹200 Cr (26.1%) from the original estimate of ₹768 Cr.
Expenditure stands at ₹509 Cr, which is 52.6% of the revised project cost.
Remaining budget: ₹459 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹768.00 Cr, later revised to ₹968.42 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi"?
- Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹768 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹768 Cr and has been revised to ₹968 Cr — a cost overrun of +26.1%. Expenditure to date: ₹509 Cr (52.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619166. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Umagaon-Saharsa Package-V Bakaur-Parsarma-Bangaon-Bariyahi & is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.