Spur to Mahishi
Original Cost
₹768 Cr
Baseline estimate
Revised Cost
₹968 Cr
Latest approved cost
Expenditure
₹411 Cr
Spent to date
Utilization
42.4%
Of revised cost
Cost Overrun
+26.1%
+₹200 Cr
Remaining
₹558 Cr
Budget left
Spent
₹411 Cr
Remaining
₹558 Cr
Total
₹968 Cr
42.4%
Utilized
Original Cost
₹768 Cr
Revised Cost
₹968 Cr
Increase
+₹200 Cr
Escalation
+26.1%
Project Approved
Construction / Implementation
Original End Date
2025-12-14
Revised Completion
2026-05-15
Completed
Cost has increased by ₹200 Cr (26.1%) from the original estimate of ₹768 Cr.
Expenditure stands at ₹411 Cr, which is 42.4% of the revised project cost.
Remaining budget: ₹558 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.