Original Cost
₹1444 Cr
Baseline estimate
Revised Cost
₹1835 Cr
Latest approved cost
Expenditure
₹872 Cr
Spent to date
Utilization
47.5%
Of revised budget
Cost Status
+27.1%
+₹391 Cr increase
Remaining
₹962 Cr
Budget left
Spent
₹872 Cr
Remaining
₹962 Cr
Total
₹1835 Cr
Original Cost
₹1444 Cr
Revised Cost
₹1835 Cr
Increase
+₹391 Cr
Escalation
+27.1%
Project Approved
Construction / Implementation
Original End Date
14/03/2023
Revised Completion
31/12/2026
Completed
Cost has increased by ₹391 Cr (27.1%) from the original estimate of ₹1444 Cr.
Expenditure stands at ₹872 Cr, which is 47.5% of the revised project cost.
Remaining budget: ₹962 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.