Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Tumkur - Nelamangala 6L
Roads & HighwaysIPM · Central Project#619071

Tumkur - Nelamangala 6L

Ministry of Road Transport & HighwaysKarnatakaData: 2026-05
Revised Cost: ₹1664 CrUtilization: 36.0%

Original Cost

₹2032 Cr

Baseline estimate

On Budget

Revised Cost

₹1664 Cr

Latest approved cost

Expenditure

₹599 Cr

Spent to date

Utilization

36.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1065 Cr

Budget left

Budget Utilization

36.0%
0%25%50%75%100%

Spent

₹599 Cr

Remaining

₹1065 Cr

Total

₹1664 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/08/2025

Revised Completion

31/03/2027

Completed

Project Details

Project Code619071
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-05

Financial & Timeline

Original Cost₹2032 Cr
Revised Cost₹1664 Cr
Expenditure₹599 Cr
Original End Date25/08/2025
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹2032 Cr — no cost escalation recorded.

Expenditure stands at ₹599 Cr, which is 36.0% of the revised project cost.

Remaining budget: ₹1065 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Frequently Asked Questions

What is IPM project "Tumkur - Nelamangala 6L"?
Tumkur - Nelamangala 6L is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹2032 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost was ₹2032 Cr and has been revised to ₹1664 Cr — a cost overrun of -18.1%. Expenditure to date: ₹599 Cr (36.0% of revised cost). Data as of 2026-05.
Which ministry is responsible for this project?
Tumkur - Nelamangala 6L is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619071. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Tumkur - Nelamangala 6L is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview