Original Cost
₹1581 Cr
Baseline estimate
Revised Cost
₹1884 Cr
Latest approved cost
Expenditure
₹940 Cr
Spent to date
Utilization
49.9%
Of revised budget
Cost Status
+19.1%
+₹303 Cr increase
Remaining
₹944 Cr
Budget left
Spent
₹940 Cr
Remaining
₹944 Cr
Total
₹1884 Cr
Original Cost
₹1581 Cr
Revised Cost
₹1884 Cr
Increase
+₹303 Cr
Escalation
+19.1%
Project Approved
Construction / Implementation
Original End Date
17/02/2023
Revised Completion
30/09/2026
Completed
Cost has increased by ₹303 Cr (19.1%) from the original estimate of ₹1581 Cr.
Expenditure stands at ₹940 Cr, which is 49.9% of the revised project cost.
Remaining budget: ₹944 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.