Roads & HighwaysIPM · Central Project +36.0% overrun#618006

Sitamarhi-Jaynagar Section km 79.400 to km 156.500 Lot-II

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹503 CrUtilization: 0.0%Overrun: +₹133 Cr

Original Cost

₹370 Cr

Baseline estimate

+36% overrun

Revised Cost

₹503 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Escalated

Cost Status

+36.0%

+₹133 Cr increase

Remaining

₹503 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹503 Cr

Total

₹503 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹370 Cr

Revised Cost

₹503 Cr

Increase

+₹133 Cr

Escalation

+36.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

29/12/2018

Revised Completion

31/07/2026

Completed

Project Details

Project Code618006
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-05

Financial Summary

Original Cost₹370 Cr
Revised Cost₹503 Cr
Expenditure₹0 Cr
Original End Date29/12/2018
Revised Date31/07/2026

Project Intelligence

Cost has increased by ₹133 Cr (36.0%) from the original estimate of ₹370 Cr.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹503 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Sitamarhi-Jaynagar Section km 79.400 to km 156.500 Lot-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹370.00 Cr, later revised to ₹503.28 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Sitamarhi-Jaynagar Section km 79.400 to km 156.500 Lot-II"?
Sitamarhi-Jaynagar Section km 79.400 to km 156.500 Lot-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹370 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹370 Cr and has been revised to ₹503 Cr — a cost overrun of +36%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Sitamarhi-Jaynagar Section km 79.400 to km 156.500 Lot-II is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618006. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sitamarhi-Jaynagar Section km 79.400 to km 156.500 Lot-II is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.