Khagaria Km. 266.282
Original Cost
₹664 Cr
Baseline estimate
Revised Cost
₹892 Cr
Latest approved cost
Expenditure
₹352 Cr
Spent to date
Utilization
39.5%
Of revised cost
Cost Overrun
+34.3%
+₹228 Cr
Remaining
₹540 Cr
Budget left
Spent
₹352 Cr
Remaining
₹540 Cr
Total
₹892 Cr
39.5%
Utilized
Original Cost
₹664 Cr
Revised Cost
₹892 Cr
Increase
+₹228 Cr
Escalation
+34.3%
Project Approved
Construction / Implementation
Original End Date
2019-04-03
Revised Completion
2026-07-31
Completed
Cost has increased by ₹228 Cr (34.3%) from the original estimate of ₹664 Cr.
Expenditure stands at ₹352 Cr, which is 39.5% of the revised project cost.
Remaining budget: ₹540 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.