Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I
Original Cost
₹179 Cr
Baseline estimate
Revised Cost
₹279 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+55.6%
+₹100 Cr increase
Remaining
₹279 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹279 Cr
Total
₹279 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹179 Cr
Revised Cost
₹279 Cr
Increase
+₹100 Cr
Escalation
+55.6%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
03/05/2018
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹100 Cr (55.6%) from the original estimate of ₹179 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹279 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹179.00 Cr, later revised to ₹278.53 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I"?
- Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹179 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹179 Cr and has been revised to ₹279 Cr — a cost overrun of +55.6%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618005. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.