79.400 km Lot-I
Original Cost
₹179 Cr
Baseline estimate
Revised Cost
₹279 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised cost
Cost Overrun
+55.6%
+₹100 Cr
Remaining
₹279 Cr
Budget left
Spent
₹0 Cr
Remaining
₹279 Cr
Total
₹279 Cr
0.0%
Utilized
Original Cost
₹179 Cr
Revised Cost
₹279 Cr
Increase
+₹100 Cr
Escalation
+55.6%
Project Approved
Construction / Implementation
Original End Date
2018-05-03
Revised Completion
2026-06-30
Completed
Cost has increased by ₹100 Cr (55.6%) from the original estimate of ₹179 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹279 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.