Roads & HighwaysIPM · Central Project#618886

Road Safety Improvement of Critical Junctions on MuzaffarnagarHaridwar Section of NH-334 from Km 143000 to Km 196000

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹0 CrUtilization: 47370.0%

Original Cost

₹239 Cr

Baseline estimate

On budget

Revised Cost

₹0 Cr

Latest approved cost

Expenditure

₹47 Cr

Spent to date

Utilization

47370.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹0 Cr

Budget left

Budget Utilization

47370.0%
0%25%50%75%100%

Spent

₹47 Cr

Remaining

₹0 Cr

Total

₹0 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/10/2027

Revised Completion

03/10/2027

Completed

Project Details

Project Code618886
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹239 Cr
Revised Cost₹0 Cr
Expenditure₹47 Cr
Original End Date03/10/2027
Revised Date03/10/2027

Project Intelligence

Project is within original budget of ₹239 Cr — no cost escalation recorded.

Expenditure stands at ₹47 Cr, which is 47370.0% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Road Safety Improvement of Critical Junctions on MuzaffarnagarHaridwar Section of NH-334 from Km 143000 to Km 196000 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹239.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Road Safety Improvement of Critical Junctions on MuzaffarnagarHaridwar Section o"?
Road Safety Improvement of Critical Junctions on MuzaffarnagarHaridwar Section of NH-334 from Km 143000 to Km 196000 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹239 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹239 Cr and has been revised to ₹0 Cr — a cost overrun of -100%. Expenditure to date: ₹47 Cr (47370.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Road Safety Improvement of Critical Junctions on Muzaffarnag is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618886. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Road Safety Improvement of Critical Junctions on Muzaffarnag is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.