Original Cost
₹6000 Cr
Baseline estimate
Revised Cost
₹6000 Cr
Latest approved cost
Expenditure
₹6000 Cr
Spent to date
Utilization
100.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Spent
₹6000 Cr
Remaining
₹0 Cr
Total
₹6000 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2023
Revised Completion
Completed
Project is within original budget of ₹6000 Cr — no cost escalation recorded.
Expenditure stands at ₹6000 Cr, which is 100.0% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Shipping. Ministry: Ministry of Ports, Shipping and Waterways.