Original Cost
₹1799 Cr
Baseline estimate
Revised Cost
₹1799 Cr
Latest approved cost
Expenditure
₹1558 Cr
Spent to date
Utilization
86.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹241 Cr
Budget left
Spent
₹1558 Cr
Remaining
₹241 Cr
Total
₹1799 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2022
Revised Completion
31/03/2025
Completed
Project is within original budget of ₹1799 Cr — no cost escalation recorded.
Expenditure stands at ₹1558 Cr, which is 86.6% of the revised project cost.
Remaining budget: ₹241 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Shipping. Ministry: Ministry of Ports, Shipping and Waterways.