Replacement and revamping of pipeline projects in oil jetty area, Kandla
Original Cost
₹171 Cr
Baseline estimate
Revised Cost
₹212 Cr
Latest approved cost
Expenditure
₹150 Cr
Spent to date
Utilization
70.6%
Of revised budget
Cost Status
+23.7%
+₹41 Cr increase
Remaining
₹62 Cr
Budget left
Budget Utilization
70.6%Spent
₹150 Cr
Remaining
₹62 Cr
Total
₹212 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹171 Cr
Revised Cost
₹212 Cr
Increase
+₹41 Cr
Escalation
+23.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/09/2023
Revised Completion
31/03/2025
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹41 Cr (23.7%) from the original estimate of ₹171 Cr.
Expenditure stands at ₹150 Cr, which is 70.6% of the revised project cost.
Remaining budget: ₹62 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Shipping. Ministry: Ministry of Ports, Shipping and Waterways.
Replacement and revamping of pipeline projects in oil jetty area, Kandla is a centrally-funded infrastructure project under Ministry of Ports, Shipping and Waterways, in the Shipping sector. The original approved cost is ₹171.00 Cr, later revised to ₹211.61 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Replacement and revamping of pipeline projects in oil jetty area, Kandla"?
- Replacement and revamping of pipeline projects in oil jetty area, Kandla is a centrally-funded infrastructure project under the Ministry of Ports, Shipping and Waterways, tracked through the Investment Project Monitoring (IPM) system. Sector: Shipping. State: Gujarat. Original cost: ₹171 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹171 Cr and has been revised to ₹212 Cr — a cost overrun of +23.7%. Expenditure to date: ₹150 Cr (70.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Replacement and revamping of pipeline projects in oil jetty is under the Ministry of Ports, Shipping and Waterways in the Shipping sector. Project code: 701570. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Replacement and revamping of pipeline projects in oil jetty is one of several Bihar projects tracked under the Shipping sector on the IPM system.