ShippingIPM · Central Project +23.7% overrun#701570

Replacement and revamping of pipeline projects in oil jetty area, Kandla

Ministry of Ports, Shipping and WaterwaysGujarat
Revised Cost: ₹212 CrUtilization: 70.6%Overrun: +₹41 Cr

Original Cost

₹171 Cr

Baseline estimate

+24% overrun

Revised Cost

₹212 Cr

Latest approved cost

Expenditure

₹150 Cr

Spent to date

Utilization

70.6%

Of revised budget

Escalated

Cost Status

+23.7%

+₹41 Cr increase

Remaining

₹62 Cr

Budget left

Budget Utilization

70.6%
0%25%50%75%100%

Spent

₹150 Cr

Remaining

₹62 Cr

Total

₹212 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹171 Cr

Revised Cost

₹212 Cr

Increase

+₹41 Cr

Escalation

+23.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/09/2023

Revised Completion

31/03/2025

Completed

Project Details

Project Code701570
SectorShipping
MinistryMinistry of Ports, Shipping and Waterways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹171 Cr
Revised Cost₹212 Cr
Expenditure₹150 Cr
Original End Date30/09/2023
Revised Date31/03/2025

Project Intelligence

Cost has increased by ₹41 Cr (23.7%) from the original estimate of ₹171 Cr.

Expenditure stands at ₹150 Cr, which is 70.6% of the revised project cost.

Remaining budget: ₹62 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Shipping. Ministry: Ministry of Ports, Shipping and Waterways.

Replacement and revamping of pipeline projects in oil jetty area, Kandla is a centrally-funded infrastructure project under Ministry of Ports, Shipping and Waterways, in the Shipping sector. The original approved cost is ₹171.00 Cr, later revised to ₹211.61 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Replacement and revamping of pipeline projects in oil jetty area, Kandla"?
Replacement and revamping of pipeline projects in oil jetty area, Kandla is a centrally-funded infrastructure project under the Ministry of Ports, Shipping and Waterways, tracked through the Investment Project Monitoring (IPM) system. Sector: Shipping. State: Gujarat. Original cost: ₹171 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹171 Cr and has been revised to ₹212 Cr — a cost overrun of +23.7%. Expenditure to date: ₹150 Cr (70.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Replacement and revamping of pipeline projects in oil jetty is under the Ministry of Ports, Shipping and Waterways in the Shipping sector. Project code: 701570. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Replacement and revamping of pipeline projects in oil jetty is one of several Bihar projects tracked under the Shipping sector on the IPM system.