Original Cost
₹171 Cr
Baseline estimate
Revised Cost
₹212 Cr
Latest approved cost
Expenditure
₹150 Cr
Spent to date
Utilization
70.6%
Of revised budget
Cost Status
+23.7%
+₹41 Cr increase
Remaining
₹62 Cr
Budget left
Spent
₹150 Cr
Remaining
₹62 Cr
Total
₹212 Cr
Original Cost
₹171 Cr
Revised Cost
₹212 Cr
Increase
+₹41 Cr
Escalation
+23.7%
Project Approved
Construction / Implementation
Original End Date
30/09/2023
Revised Completion
31/03/2025
Completed
Cost has increased by ₹41 Cr (23.7%) from the original estimate of ₹171 Cr.
Expenditure stands at ₹150 Cr, which is 70.6% of the revised project cost.
Remaining budget: ₹62 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Shipping. Ministry: Ministry of Ports, Shipping and Waterways.