Rehabilitation & upgradation of existing road to 2-lane with hard shoulder from Joshimath km 0.00 to Saraithota km 29.725 road on NH-107B under Bharatmala Pariyojna on EPC mode in the state of Uttarakhand
Original Cost
₹338 Cr
Baseline estimate
Revised Cost
₹338 Cr
Latest approved cost
Expenditure
₹159 Cr
Spent to date
Utilization
47.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹179 Cr
Budget left
Budget Utilization
47.1%Spent
₹159 Cr
Remaining
₹179 Cr
Total
₹338 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
21/05/2025
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹338 Cr — no cost escalation recorded.
Expenditure stands at ₹159 Cr, which is 47.1% of the revised project cost.
Remaining budget: ₹179 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation & upgradation of existing road to 2-lane with hard shoulder from Joshimath km 0.00 to Saraithota km 29.725 road on NH-107B under Bharatmala Pariyojna on EPC mode in the state of Uttarakhand is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹338.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation & upgradation of existing road to 2-lane with hard shoulder from "?
- Rehabilitation & upgradation of existing road to 2-lane with hard shoulder from Joshimath km 0.00 to Saraithota km 29.725 road on NH-107B under Bharatmala Pariyojna on EPC mode in the state of Uttarakhand is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹338 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹338 Cr has not been significantly revised. Expenditure: ₹159 Cr (47.1% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation & upgradation of existing road to 2-lane with is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618218. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation & upgradation of existing road to 2-lane with is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.