Rehabilitation and Upgrading of NH-707 OLD 72-B Package - 2 Hewna to Ashyari
Original Cost
₹243 Cr
Baseline estimate
Revised Cost
₹221 Cr
Latest approved cost
Expenditure
₹145 Cr
Spent to date
Utilization
65.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹75 Cr
Budget left
Budget Utilization
65.8%Spent
₹145 Cr
Remaining
₹75 Cr
Total
₹221 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
23/03/2023
Revised Completion
31/12/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹243 Cr — no cost escalation recorded.
Expenditure stands at ₹145 Cr, which is 65.8% of the revised project cost.
Remaining budget: ₹75 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Upgrading of NH-707 OLD 72-B Package - 2 Hewna to Ashyari is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹243.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Upgrading of NH-707 OLD 72-B Package - 2 Hewna to Ashyari"?
- Rehabilitation and Upgrading of NH-707 OLD 72-B Package - 2 Hewna to Ashyari is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹243 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹243 Cr and has been revised to ₹221 Cr — a cost overrun of -9.1%. Expenditure to date: ₹145 Cr (65.8% of revised cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Rehabilitation and Upgrading of NH-707 OLD 72-B Package - 2 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618051. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgrading of NH-707 OLD 72-B Package - 2 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.