Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Koyyuru to Chaprathipalem section Km 120000 to Km 165500 of NH-516E in the State of Andhra Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode
Original Cost
₹349 Cr
Baseline estimate
Revised Cost
₹349 Cr
Latest approved cost
Expenditure
₹268 Cr
Spent to date
Utilization
76.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹81 Cr
Budget left
Budget Utilization
76.7%Spent
₹268 Cr
Remaining
₹81 Cr
Total
₹349 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
07/07/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹349 Cr — no cost escalation recorded.
Expenditure stands at ₹268 Cr, which is 76.7% of the revised project cost.
Remaining budget: ₹81 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Koyyuru to Chaprathipalem section Km 120000 to Km 165500 of NH-516E in the State of Andhra Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹349.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of K"?
- Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Koyyuru to Chaprathipalem section Km 120000 to Km 165500 of NH-516E in the State of Andhra Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹349 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹349 Cr has not been significantly revised. Expenditure: ₹268 Cr (76.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and Upgradation to 2-lane with paved shoulder is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618257. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation to 2-lane with paved shoulder is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.