Roads & HighwaysIPM · Central Project#618221

Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 166.100 to Km 192.98 design chainage Km 146.700 to Km 162.800 including construction of Bhimber Gali Tunnel Total Length of Tunnel 1.100 Km under 31 BRTF on Akhnoor-Poonch Roads on EPC mode NH-144A Package-VII

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹735 CrUtilization: 33.1%

Original Cost

₹735 Cr

Baseline estimate

On budget

Revised Cost

₹735 Cr

Latest approved cost

Expenditure

₹243 Cr

Spent to date

Utilization

33.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹492 Cr

Budget left

Budget Utilization

33.1%
0%25%50%75%100%

Spent

₹243 Cr

Remaining

₹492 Cr

Total

₹735 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/07/2026

Revised Completion

31/07/2027

Completed

Project Details

Project Code618221
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹735 Cr
Revised Cost₹735 Cr
Expenditure₹243 Cr
Original End Date30/07/2026
Revised Date31/07/2027

Project Intelligence

Project is within original budget of ₹735 Cr — no cost escalation recorded.

Expenditure stands at ₹243 Cr, which is 33.1% of the revised project cost.

Remaining budget: ₹492 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 166.100 to Km 192.98 design chainage Km 146.700 to Km 162.800 including construction of Bhimber Gali Tunnel Total Length of Tunnel 1.100 Km under 31 BRTF on Akhnoor-Poonch Roads on EPC mode NH-144A Package-VII is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹735.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and upgradation to 2 lane with paved shoulder from existing chain"?
Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 166.100 to Km 192.98 design chainage Km 146.700 to Km 162.800 including construction of Bhimber Gali Tunnel Total Length of Tunnel 1.100 Km under 31 BRTF on Akhnoor-Poonch Roads on EPC mode NH-144A Package-VII is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹735 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹735 Cr has not been significantly revised. Expenditure: ₹243 Cr (33.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and upgradation to 2 lane with paved shoulder is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618221. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and upgradation to 2 lane with paved shoulder is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.