Original Cost
₹252 Cr
Baseline estimate
Revised Cost
₹190 Cr
Latest approved cost
Expenditure
₹76 Cr
Spent to date
Utilization
39.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹114 Cr
Budget left
Spent
₹76 Cr
Remaining
₹114 Cr
Total
₹190 Cr
Project Approved
Construction / Implementation
Original End Date
14/05/2026
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹252 Cr — no cost escalation recorded.
Expenditure stands at ₹76 Cr, which is 39.9% of the revised project cost.
Remaining budget: ₹114 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.