Rehabilitation and Upgradation to 2-lane configuration of Karnohal- Kalwahn Section km 181.00 to 208.950 of NH-70 in the State of Himachal Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode.Package-2
Original Cost
₹252 Cr
Baseline estimate
Revised Cost
₹190 Cr
Latest approved cost
Expenditure
₹122 Cr
Spent to date
Utilization
64.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹68 Cr
Budget left
Budget Utilization
64.0%Spent
₹122 Cr
Remaining
₹68 Cr
Total
₹190 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
14/05/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹252 Cr — no cost escalation recorded.
Expenditure stands at ₹122 Cr, which is 64.0% of the revised project cost.
Remaining budget: ₹68 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Upgradation to 2-lane configuration of Karnohal- Kalwahn Section km 181.00 to 208.950 of NH-70 in the State of Himachal Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode.Package-2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹252.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Upgradation to 2-lane configuration of Karnohal- Kalwahn Sect"?
- Rehabilitation and Upgradation to 2-lane configuration of Karnohal- Kalwahn Section km 181.00 to 208.950 of NH-70 in the State of Himachal Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode.Package-2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹252 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹252 Cr and has been revised to ₹190 Cr — a cost overrun of -24.6%. Expenditure to date: ₹122 Cr (64.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and Upgradation to 2-lane configuration of Ka is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618232. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation to 2-lane configuration of Ka is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.