Rehabilitation and Upgradation of Satana to Mangrul Chandwad Section of NH752 G Design Ch Km 64.000 to Ch Km 101.140 two lane with paved shoulder/four lane configuration in the state of Maharashtra on EPC mode.
Original Cost
₹429 Cr
Baseline estimate
Revised Cost
₹429 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹429 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹429 Cr
Total
₹429 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
14/05/2025
Revised Completion
30/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹429 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹429 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Upgradation of Satana to Mangrul Chandwad Section of NH752 G Design Ch Km 64.000 to Ch Km 101.140 two lane with paved shoulder/four lane configuration in the state of Maharashtra on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹429.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Upgradation of Satana to Mangrul Chandwad Section of NH752 G "?
- Rehabilitation and Upgradation of Satana to Mangrul Chandwad Section of NH752 G Design Ch Km 64.000 to Ch Km 101.140 two lane with paved shoulder/four lane configuration in the state of Maharashtra on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹429 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹429 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Rehabilitation and Upgradation of Satana to Mangrul Chandwad is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618175. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation of Satana to Mangrul Chandwad is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.