Original Cost
₹295 Cr
Baseline estimate
Revised Cost
₹335 Cr
Latest approved cost
Expenditure
₹375 Cr
Spent to date
Utilization
112.0%
Of revised budget
Cost Status
+13.5%
+₹40 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹375 Cr
Remaining
₹0 Cr
Total
₹335 Cr
Original Cost
₹295 Cr
Revised Cost
₹335 Cr
Increase
+₹40 Cr
Escalation
+13.5%
Project Approved
Construction / Implementation
Original End Date
24/02/2017
Revised Completion
30/06/2026
Completed
Cost has increased by ₹40 Cr (13.5%) from the original estimate of ₹295 Cr.
Expenditure stands at ₹375 Cr, which is 112.0% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.