Roads & HighwaysIPM · Central Project +13.5% overrun#619193

Rehabilitation and upgradation of NH-221 from km 121/0 to 165/0 Rudrampur to Bhadrachalam section to two lane with paved shoulder under NHDPIV in the state of Telangana through EPC mode

Ministry of Road Transport & HighwaysTelangana
Revised Cost: ₹335 CrUtilization: 62.7%Overrun: +₹40 Cr

Original Cost

₹295 Cr

Baseline estimate

+14% overrun

Revised Cost

₹335 Cr

Latest approved cost

Expenditure

₹210 Cr

Spent to date

Utilization

62.7%

Of revised budget

Escalated

Cost Status

+13.5%

+₹40 Cr increase

Remaining

₹125 Cr

Budget left

Budget Utilization

62.7%
0%25%50%75%100%

Spent

₹210 Cr

Remaining

₹125 Cr

Total

₹335 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹295 Cr

Revised Cost

₹335 Cr

Increase

+₹40 Cr

Escalation

+13.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/02/2017

Revised Completion

30/09/2026

Completed

Project Details

Project Code619193
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹295 Cr
Revised Cost₹335 Cr
Expenditure₹210 Cr
Original End Date24/02/2017
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹40 Cr (13.5%) from the original estimate of ₹295 Cr.

Expenditure stands at ₹210 Cr, which is 62.7% of the revised project cost.

Remaining budget: ₹125 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and upgradation of NH-221 from km 121/0 to 165/0 Rudrampur to Bhadrachalam section to two lane with paved shoulder under NHDPIV in the state of Telangana through EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹295.00 Cr, later revised to ₹334.82 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and upgradation of NH-221 from km 121/0 to 165/0 Rudrampur to Bha"?
Rehabilitation and upgradation of NH-221 from km 121/0 to 165/0 Rudrampur to Bhadrachalam section to two lane with paved shoulder under NHDPIV in the state of Telangana through EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹295 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹295 Cr and has been revised to ₹335 Cr — a cost overrun of +13.5%. Expenditure to date: ₹210 Cr (62.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and upgradation of NH-221 from km 121/0 to 16 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619193. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and upgradation of NH-221 from km 121/0 to 16 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.