Roads & HighwaysIPM · Central Project#618307

Rehabilitation and up-gradation of road from km 16.077 to km 43.935 total length 27.858 km of Lalchara-Kanchanpur section via Shivbari on NH-44A to 2 lane with paved shoulder in the state of Tripura on EPC Mode Pkg-2 under BharatMala Pariyojana Manu-Simlung -2

Ministry of Road Transport & HighwaysTripura
Revised Cost: ₹457 CrUtilization: 45.0%

Original Cost

₹457 Cr

Baseline estimate

On budget

Revised Cost

₹457 Cr

Latest approved cost

Expenditure

₹206 Cr

Spent to date

Utilization

45.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹251 Cr

Budget left

Budget Utilization

45.0%
0%25%50%75%100%

Spent

₹206 Cr

Remaining

₹251 Cr

Total

₹457 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

09/01/2025

Revised Completion

26/01/2026

Completed

Project Details

Project Code618307
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTripura
Data Month2026-08

Financial Summary

Original Cost₹457 Cr
Revised Cost₹457 Cr
Expenditure₹206 Cr
Original End Date09/01/2025
Revised Date26/01/2026

Project Intelligence

Project is within original budget of ₹457 Cr — no cost escalation recorded.

Expenditure stands at ₹206 Cr, which is 45.0% of the revised project cost.

Remaining budget: ₹251 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and up-gradation of road from km 16.077 to km 43.935 total length 27.858 km of Lalchara-Kanchanpur section via Shivbari on NH-44A to 2 lane with paved shoulder in the state of Tripura on EPC Mode Pkg-2 under BharatMala Pariyojana Manu-Simlung -2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹457.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and up-gradation of road from km 16.077 to km 43.935 total length"?
Rehabilitation and up-gradation of road from km 16.077 to km 43.935 total length 27.858 km of Lalchara-Kanchanpur section via Shivbari on NH-44A to 2 lane with paved shoulder in the state of Tripura on EPC Mode Pkg-2 under BharatMala Pariyojana Manu-Simlung -2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tripura. Original cost: ₹457 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹457 Cr has not been significantly revised. Expenditure: ₹206 Cr (45.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and up-gradation of road from km 16.077 to km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618307. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and up-gradation of road from km 16.077 to km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.