Roads & HighwaysIPM · Central Project#617991

Rehabilitation and up-gradation of NH-167 from Km 14/900 to Km70/000 Design Ch. 14/900 to 69/700 Chintakunta to Adoni section to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through Engineering, Procurement

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹290 CrUtilization: 70.7%

Original Cost

₹290 Cr

Baseline estimate

On budget

Revised Cost

₹290 Cr

Latest approved cost

Expenditure

₹205 Cr

Spent to date

Utilization

70.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹85 Cr

Budget left

Budget Utilization

70.7%
0%25%50%75%100%

Spent

₹205 Cr

Remaining

₹85 Cr

Total

₹290 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/05/2019

Revised Completion

31/12/2026

Completed

Project Details

Project Code617991
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹290 Cr
Revised Cost₹290 Cr
Expenditure₹205 Cr
Original End Date30/05/2019
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹290 Cr — no cost escalation recorded.

Expenditure stands at ₹205 Cr, which is 70.7% of the revised project cost.

Remaining budget: ₹85 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and up-gradation of NH-167 from Km 14/900 to Km70/000 Design Ch. 14/900 to 69/700 Chintakunta to Adoni section to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through Engineering, Procurement is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹290.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and up-gradation of NH-167 from Km 14/900 to Km70/000 Design Ch. "?
Rehabilitation and up-gradation of NH-167 from Km 14/900 to Km70/000 Design Ch. 14/900 to 69/700 Chintakunta to Adoni section to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through Engineering, Procurement is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹290 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹290 Cr has not been significantly revised. Expenditure: ₹205 Cr (70.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and up-gradation of NH-167 from Km 14/900 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617991. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and up-gradation of NH-167 from Km 14/900 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.