Rehabilitation and up-gradation and completion of balance works of the section from Km 107.760 km to 129.445 km After Middle strait to Humphrey, Km 130.600 to 138.300 After Humphrey to Kadamtala of NH-4 Intermediate/2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC basis Package-IIIA
Original Cost
₹207 Cr
Baseline estimate
Revised Cost
₹376 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+81.9%
+₹169 Cr increase
Remaining
₹376 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹376 Cr
Total
₹376 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹207 Cr
Revised Cost
₹376 Cr
Increase
+₹169 Cr
Escalation
+81.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/09/2025
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹169 Cr (81.9%) from the original estimate of ₹207 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹376 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and up-gradation and completion of balance works of the section from Km 107.760 km to 129.445 km After Middle strait to Humphrey, Km 130.600 to 138.300 After Humphrey to Kadamtala of NH-4 Intermediate/2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC basis Package-IIIA is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹207.00 Cr, later revised to ₹376.48 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and up-gradation and completion of balance works of the section f"?
- Rehabilitation and up-gradation and completion of balance works of the section from Km 107.760 km to 129.445 km After Middle strait to Humphrey, Km 130.600 to 138.300 After Humphrey to Kadamtala of NH-4 Intermediate/2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC basis Package-IIIA is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andaman & Nicobar. Original cost: ₹207 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹207 Cr and has been revised to ₹376 Cr — a cost overrun of +81.9%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and up-gradation and completion of balance wo is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619184. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and up-gradation and completion of balance wo is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.