Roads & HighwaysIPM · Central Project#618025

Rehabiitation and upgradation from km 121/000 to 154/000 Nakrekal to Mallampally section of NH-365 to 2 lane with paved shoulders in the state of Telangana in the EPC mode

Ministry of Road Transport & HighwaysTelangana
Revised Cost: ₹193 CrUtilization: 89.1%

Original Cost

₹193 Cr

Baseline estimate

On budget

Revised Cost

₹193 Cr

Latest approved cost

Expenditure

₹172 Cr

Spent to date

Utilization

89.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹21 Cr

Budget left

Budget Utilization

89.1%
0%25%50%75%100%

Spent

₹172 Cr

Remaining

₹21 Cr

Total

₹193 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/12/2019

Revised Completion

30/09/2026

Completed

Project Details

Project Code618025
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹193 Cr
Revised Cost₹193 Cr
Expenditure₹172 Cr
Original End Date08/12/2019
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹193 Cr — no cost escalation recorded.

Expenditure stands at ₹172 Cr, which is 89.1% of the revised project cost.

Remaining budget: ₹21 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabiitation and upgradation from km 121/000 to 154/000 Nakrekal to Mallampally section of NH-365 to 2 lane with paved shoulders in the state of Telangana in the EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹193.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabiitation and upgradation from km 121/000 to 154/000 Nakrekal to Mallampally"?
Rehabiitation and upgradation from km 121/000 to 154/000 Nakrekal to Mallampally section of NH-365 to 2 lane with paved shoulders in the state of Telangana in the EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹193 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹193 Cr has not been significantly revised. Expenditure: ₹172 Cr (89.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabiitation and upgradation from km 121/000 to 154/000 Nak is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618025. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabiitation and upgradation from km 121/000 to 154/000 Nak is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.