Roads & HighwaysIPM · Central Project#617970

Reconstruction of existing 2 L/IL to 2L with paved shoulder from existing km 52.200 to 92.880 of NH-

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹282 CrUtilization: 58.9%

Original Cost

₹282 Cr

Baseline estimate

On budget

Revised Cost

₹282 Cr

Latest approved cost

Expenditure

₹166 Cr

Spent to date

Utilization

58.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹116 Cr

Budget left

Budget Utilization

58.9%
0%25%50%75%100%

Spent

₹166 Cr

Remaining

₹116 Cr

Total

₹282 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

18/06/2019

Revised Completion

20/10/2023

Completed

Project Details

Project Code617970
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-05

Financial Summary

Original Cost₹282 Cr
Revised Cost₹282 Cr
Expenditure₹166 Cr
Original End Date18/06/2019
Revised Date20/10/2023

Project Intelligence

Project is within original budget of ₹282 Cr — no cost escalation recorded.

Expenditure stands at ₹166 Cr, which is 58.9% of the revised project cost.

Remaining budget: ₹116 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Reconstruction of existing 2 L/IL to 2L with paved shoulder from existing km 52.200 to 92.880 of NH- is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹282.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Reconstruction of existing 2 L/IL to 2L with paved shoulder from existing km 52."?
Reconstruction of existing 2 L/IL to 2L with paved shoulder from existing km 52.200 to 92.880 of NH- is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹282 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹282 Cr has not been significantly revised. Expenditure: ₹166 Cr (58.9% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Reconstruction of existing 2 L/IL to 2L with paved shoulder is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617970. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Reconstruction of existing 2 L/IL to 2L with paved shoulder is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.