Provision of 4G Mobile Services in Uncovered Villages of Arunachal Pradesh and 2 Districts of Assam
Original Cost
₹1255 Cr
Baseline estimate
Revised Cost
₹277 Cr
Latest approved cost
Expenditure
₹238 Cr
Spent to date
Utilization
86.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹39 Cr
Budget left
Budget Utilization
86.0%Spent
₹238 Cr
Remaining
₹39 Cr
Total
₹277 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/04/2023
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1255 Cr — no cost escalation recorded.
Expenditure stands at ₹238 Cr, which is 86.0% of the revised project cost.
Remaining budget: ₹39 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Telecommunication. Ministry: Department of Telecommunications.
Provision of 4G Mobile Services in Uncovered Villages of Arunachal Pradesh and 2 Districts of Assam is a centrally-funded infrastructure project under Department of Telecommunications, in the Telecommunication sector. The original approved cost is ₹1255.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Provision of 4G Mobile Services in Uncovered Villages of Arunachal Pradesh and 2"?
- Provision of 4G Mobile Services in Uncovered Villages of Arunachal Pradesh and 2 Districts of Assam is a centrally-funded infrastructure project under the Department of Telecommunications, tracked through the Investment Project Monitoring (IPM) system. Sector: Telecommunication. State: Assam. Original cost: ₹1255 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1255 Cr and has been revised to ₹277 Cr — a cost overrun of -78%. Expenditure to date: ₹238 Cr (86.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Provision of 4G Mobile Services in Uncovered Villages of Aru is under the Department of Telecommunications in the Telecommunication sector. Project code: 701597. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Provision of 4G Mobile Services in Uncovered Villages of Aru is one of several Bihar projects tracked under the Telecommunication sector on the IPM system.