Scheme
Original Cost
₹337 Cr
Baseline estimate
Revised Cost
₹301 Cr
Latest approved cost
Expenditure
₹241 Cr
Spent to date
Utilization
80.1%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹60 Cr
Budget left
Spent
₹241 Cr
Remaining
₹60 Cr
Total
₹301 Cr
80.1%
Utilized
Project Approved
Construction / Implementation
Original End Date
2021-10-27
Revised Completion
2025-08-31
Completed
Project is within original budget of ₹337 Cr — no cost escalation recorded.
Expenditure stands at ₹241 Cr, which is 80.1% of the revised project cost.
Remaining budget: ₹60 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Telecommunication. Ministry: Department of Telecommunications.