Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two lane with paved shoulders of NH 122B from km 29.730 to km 72.348 in state of Bihar under EPC mode
Original Cost
₹624 Cr
Baseline estimate
Revised Cost
₹624 Cr
Latest approved cost
Expenditure
₹393 Cr
Spent to date
Utilization
62.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹231 Cr
Budget left
Budget Utilization
62.9%Spent
₹393 Cr
Remaining
₹231 Cr
Total
₹624 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
07/08/2026
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹624 Cr — no cost escalation recorded.
Expenditure stands at ₹393 Cr, which is 62.9% of the revised project cost.
Remaining budget: ₹231 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two lane with paved shoulders of NH 122B from km 29.730 to km 72.348 in state of Bihar under EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹624.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two"?
- Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two lane with paved shoulders of NH 122B from km 29.730 to km 72.348 in state of Bihar under EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹624 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹624 Cr has not been significantly revised. Expenditure: ₹393 Cr (62.9% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Pre construction activity of NH 122B from km 0 to 72.348 and is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618074. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pre construction activity of NH 122B from km 0 to 72.348 and is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.