NH 122B from km 29.730 to km 72.348 in state of Bihar under EPC mode
Original Cost
₹624 Cr
Baseline estimate
Revised Cost
₹624 Cr
Latest approved cost
Expenditure
₹153 Cr
Spent to date
Utilization
24.6%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹471 Cr
Budget left
Spent
₹153 Cr
Remaining
₹471 Cr
Total
₹624 Cr
24.6%
Utilized
Project Approved
Construction / Implementation
Original End Date
2024-11-11
Revised Completion
2026-06-30
Completed
Project is within original budget of ₹624 Cr — no cost escalation recorded.
Expenditure stands at ₹153 Cr, which is 24.6% of the revised project cost.
Remaining budget: ₹471 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.