Roads & HighwaysIPM · Central Project#618074

Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two lane with paved shoulders of NH 122B from km 29.730 to km 72.348 in state of Bihar under EPC mode

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹624 CrUtilization: 62.9%

Original Cost

₹624 Cr

Baseline estimate

On budget

Revised Cost

₹624 Cr

Latest approved cost

Expenditure

₹393 Cr

Spent to date

Utilization

62.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹231 Cr

Budget left

Budget Utilization

62.9%
0%25%50%75%100%

Spent

₹393 Cr

Remaining

₹231 Cr

Total

₹624 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/08/2026

Revised Completion

31/10/2026

Completed

Project Details

Project Code618074
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹624 Cr
Revised Cost₹624 Cr
Expenditure₹393 Cr
Original End Date07/08/2026
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹624 Cr — no cost escalation recorded.

Expenditure stands at ₹393 Cr, which is 62.9% of the revised project cost.

Remaining budget: ₹231 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two lane with paved shoulders of NH 122B from km 29.730 to km 72.348 in state of Bihar under EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹624.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two"?
Pre construction activity of NH 122B from km 0 to 72.348 and Improvement to two lane with paved shoulders of NH 122B from km 29.730 to km 72.348 in state of Bihar under EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹624 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹624 Cr has not been significantly revised. Expenditure: ₹393 Cr (62.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Pre construction activity of NH 122B from km 0 to 72.348 and is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618074. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pre construction activity of NH 122B from km 0 to 72.348 and is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.