Original Cost
₹911 Cr
Baseline estimate
Revised Cost
₹1299 Cr
Latest approved cost
Expenditure
₹1073 Cr
Spent to date
Utilization
82.6%
Of revised budget
Cost Status
+42.6%
+₹388 Cr increase
Remaining
₹226 Cr
Budget left
Spent
₹1073 Cr
Remaining
₹226 Cr
Total
₹1299 Cr
Original Cost
₹911 Cr
Revised Cost
₹1299 Cr
Increase
+₹388 Cr
Escalation
+42.6%
Project Approved
Construction / Implementation
Original End Date
31/01/2024
Revised Completion
15/02/2026
Completed
Cost has increased by ₹388 Cr (42.6%) from the original estimate of ₹911 Cr.
Expenditure stands at ₹1073 Cr, which is 82.6% of the revised project cost.
Remaining budget: ₹226 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.