Original Cost
₹1459 Cr
Baseline estimate
Revised Cost
₹2531 Cr
Latest approved cost
Expenditure
₹1632 Cr
Spent to date
Utilization
64.5%
Of revised budget
Cost Status
+73.5%
+₹1072 Cr increase
Remaining
₹899 Cr
Budget left
Spent
₹1632 Cr
Remaining
₹899 Cr
Total
₹2531 Cr
Original Cost
₹1459 Cr
Revised Cost
₹2531 Cr
Increase
+₹1072 Cr
Escalation
+73.5%
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/12/2026
Completed
Cost has increased by ₹1072 Cr (73.5%) from the original estimate of ₹1459 Cr.
Expenditure stands at ₹1632 Cr, which is 64.5% of the revised project cost.
Remaining budget: ₹899 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.