Pipeline Network Project Rudrasagar

Ministry of Petroleum & Natural GasAssam
Revised Cost: ₹481 CrUtilization: 49.6%

Original Cost

₹481 Cr

Baseline estimate

On budget

Revised Cost

₹481 Cr

Latest approved cost

Expenditure

₹239 Cr

Spent to date

Utilization

49.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹242 Cr

Budget left

Budget Utilization

49.6%
0%25%50%75%100%

Spent

₹239 Cr

Remaining

₹242 Cr

Total

₹481 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/04/2026

Revised Completion

30/04/2027

Completed

Project Details

Project Code709847
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹481 Cr
Revised Cost₹481 Cr
Expenditure₹239 Cr
Original End Date27/04/2026
Revised Date30/04/2027

Project Intelligence

Project is within original budget of ₹481 Cr — no cost escalation recorded.

Expenditure stands at ₹239 Cr, which is 49.6% of the revised project cost.

Remaining budget: ₹242 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Pipeline Network Project Rudrasagar is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹481.00 Cr, later revised to ₹481.03 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Pipeline Network Project Rudrasagar"?
Pipeline Network Project Rudrasagar is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Assam. Original cost: ₹481 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹481 Cr has not been significantly revised. Expenditure: ₹239 Cr (49.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Pipeline Network Project Rudrasagar is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 709847. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pipeline Network Project Rudrasagar is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.