PHASE-I OF CONSOLIDATION OF EXISTING CDR DATA CENTERS AND NIB-P3 DATA CENTERS WITH STATE OF THE ART
Original Cost
₹461 Cr
Baseline estimate
Revised Cost
₹461 Cr
Latest approved cost
Expenditure
₹166 Cr
Spent to date
Utilization
36.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹295 Cr
Budget left
Budget Utilization
36.0%Spent
₹166 Cr
Remaining
₹295 Cr
Total
₹461 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
18/06/2021
Revised Completion
31/12/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹461 Cr — no cost escalation recorded.
Expenditure stands at ₹166 Cr, which is 36.0% of the revised project cost.
Remaining budget: ₹295 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Telecommunication. Ministry: Department of Telecommunications.
PHASE-I OF CONSOLIDATION OF EXISTING CDR DATA CENTERS AND NIB-P3 DATA CENTERS WITH STATE OF THE ART is a centrally-funded infrastructure project under Department of Telecommunications, in the Telecommunication sector. The original approved cost is ₹461.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "PHASE-I OF CONSOLIDATION OF EXISTING CDR DATA CENTERS AND NIB-P3 DATA CENTERS WI"?
- PHASE-I OF CONSOLIDATION OF EXISTING CDR DATA CENTERS AND NIB-P3 DATA CENTERS WITH STATE OF THE ART is a centrally-funded infrastructure project under the Department of Telecommunications, tracked through the Investment Project Monitoring (IPM) system. Sector: Telecommunication. State: Maharashtra. Original cost: ₹461 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹461 Cr has not been significantly revised. Expenditure: ₹166 Cr (36.0% of cost). Data as of 2026-02.
- QWhich ministry is responsible for this project?
- PHASE-I OF CONSOLIDATION OF EXISTING CDR DATA CENTERS AND NI is under the Department of Telecommunications in the Telecommunication sector. Project code: 709749. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. PHASE-I OF CONSOLIDATION OF EXISTING CDR DATA CENTERS AND NI is one of several Bihar projects tracked under the Telecommunication sector on the IPM system.