Original Cost
₹13.6K Cr
Baseline estimate
Revised Cost
₹13.6K Cr
Latest approved cost
Expenditure
₹64 Cr
Spent to date
Utilization
0.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹13.6K Cr
Budget left
Spent
₹64 Cr
Remaining
₹13.6K Cr
Total
₹13.6K Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2029
Revised Completion
30/09/2029
Completed
Mega infrastructure project worth ₹13.6K Cr — among the largest central projects in Maharashtra.
Project is within original budget of ₹13.6K Cr — no cost escalation recorded.
Expenditure stands at ₹64 Cr, which is 0.5% of the revised project cost.
Remaining budget: ₹13.6K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.