Original Cost
₹369 Cr
Baseline estimate
Revised Cost
₹369 Cr
Latest approved cost
Expenditure
₹330 Cr
Spent to date
Utilization
89.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹39 Cr
Budget left
Spent
₹330 Cr
Remaining
₹39 Cr
Total
₹369 Cr
Project Approved
Construction / Implementation
Original End Date
21/12/2019
Revised Completion
31/12/2025
Completed
Project is within original budget of ₹369 Cr — no cost escalation recorded.
Expenditure stands at ₹330 Cr, which is 89.5% of the revised project cost.
Remaining budget: ₹39 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.