Original Cost
₹1219 Cr
Baseline estimate
Revised Cost
₹1145 Cr
Latest approved cost
Expenditure
₹820 Cr
Spent to date
Utilization
71.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹325 Cr
Budget left
Spent
₹820 Cr
Remaining
₹325 Cr
Total
₹1145 Cr
Project Approved
Construction / Implementation
Original End Date
15/05/2024
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹1219 Cr — no cost escalation recorded.
Expenditure stands at ₹820 Cr, which is 71.6% of the revised project cost.
Remaining budget: ₹325 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.