Original Cost
₹3420 Cr
Baseline estimate
Revised Cost
₹4466 Cr
Latest approved cost
Expenditure
₹1923 Cr
Spent to date
Utilization
43.1%
Of revised budget
Cost Status
+30.6%
+₹1046 Cr increase
Remaining
₹2543 Cr
Budget left
Spent
₹1923 Cr
Remaining
₹2543 Cr
Total
₹4466 Cr
Original Cost
₹3420 Cr
Revised Cost
₹4466 Cr
Increase
+₹1046 Cr
Escalation
+30.6%
Project Approved
Construction / Implementation
Original End Date
23/09/2021
Revised Completion
31/03/2027
Completed
Cost has increased by ₹1046 Cr (30.6%) from the original estimate of ₹3420 Cr.
Expenditure stands at ₹1923 Cr, which is 43.1% of the revised project cost.
Remaining budget: ₹2543 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.