Roads & HighwaysIPM · Central Project#618172

Paithan - Shirur section 2LPS Km 0.0 to 55.00

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹342 CrUtilization: 74.2%

Original Cost

₹342 Cr

Baseline estimate

On budget

Revised Cost

₹342 Cr

Latest approved cost

Expenditure

₹254 Cr

Spent to date

Utilization

74.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹88 Cr

Budget left

Budget Utilization

74.2%
0%25%50%75%100%

Spent

₹254 Cr

Remaining

₹88 Cr

Total

₹342 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/06/2019

Revised Completion

30/10/2026

Completed

Project Details

Project Code618172
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹342 Cr
Revised Cost₹342 Cr
Expenditure₹254 Cr
Original End Date02/06/2019
Revised Date30/10/2026

Project Intelligence

Project is within original budget of ₹342 Cr — no cost escalation recorded.

Expenditure stands at ₹254 Cr, which is 74.2% of the revised project cost.

Remaining budget: ₹88 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Paithan - Shirur section 2LPS Km 0.0 to 55.00 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹342.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Paithan - Shirur section 2LPS Km 0.0 to 55.00"?
Paithan - Shirur section 2LPS Km 0.0 to 55.00 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹342 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹342 Cr has not been significantly revised. Expenditure: ₹254 Cr (74.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Paithan - Shirur section 2LPS Km 0.0 to 55.00 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618172. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Paithan - Shirur section 2LPS Km 0.0 to 55.00 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.