Original Cost
₹911 Cr
Baseline estimate
Revised Cost
₹773 Cr
Latest approved cost
Expenditure
₹503 Cr
Spent to date
Utilization
65.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹271 Cr
Budget left
Spent
₹503 Cr
Remaining
₹271 Cr
Total
₹773 Cr
Project Approved
Construction / Implementation
Original End Date
04/03/2026
Revised Completion
27/10/2026
Completed
Project is within original budget of ₹911 Cr — no cost escalation recorded.
Expenditure stands at ₹503 Cr, which is 65.0% of the revised project cost.
Remaining budget: ₹271 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.