Original Cost
₹917 Cr
Baseline estimate
Revised Cost
₹786 Cr
Latest approved cost
Expenditure
₹499 Cr
Spent to date
Utilization
63.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹287 Cr
Budget left
Spent
₹499 Cr
Remaining
₹287 Cr
Total
₹786 Cr
Project Approved
Construction / Implementation
Original End Date
07/03/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹917 Cr — no cost escalation recorded.
Expenditure stands at ₹499 Cr, which is 63.5% of the revised project cost.
Remaining budget: ₹287 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.