Roads & HighwaysIPM · Central Project +0.9% overrun#619320

Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹2311 CrUtilization: 20.3%Overrun: +₹20 Cr

Original Cost

₹2291 Cr

Baseline estimate

+1% overrun

Revised Cost

₹2311 Cr

Latest approved cost

Expenditure

₹469 Cr

Spent to date

Utilization

20.3%

Of revised budget

Escalated

Cost Status

+0.9%

+₹20 Cr increase

Remaining

₹1842 Cr

Budget left

Budget Utilization

20.3%
0%25%50%75%100%

Spent

₹469 Cr

Remaining

₹1842 Cr

Total

₹2311 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2291 Cr

Revised Cost

₹2311 Cr

Increase

+₹20 Cr

Escalation

+0.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/11/2013

Revised Completion

30/06/2026

Completed

Project Details

Project Code619320
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-05

Financial Summary

Original Cost₹2291 Cr
Revised Cost₹2311 Cr
Expenditure₹469 Cr
Original End Date25/11/2013
Revised Date30/06/2026

Project Intelligence

Cost has increased by ₹20 Cr (0.9%) from the original estimate of ₹2291 Cr.

Expenditure stands at ₹469 Cr, which is 20.3% of the revised project cost.

Remaining budget: ₹1842 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2291.00 Cr, later revised to ₹2311.10 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000"?
Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹2291 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2291 Cr and has been revised to ₹2311 Cr — a cost overrun of +0.9%. Expenditure to date: ₹469 Cr (20.3% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619320. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.