km 2.800 to km 89.000
Original Cost
₹2291 Cr
Baseline estimate
Revised Cost
₹2311 Cr
Latest approved cost
Expenditure
₹469 Cr
Spent to date
Utilization
20.3%
Of revised cost
Cost Overrun
+0.9%
+₹20 Cr
Remaining
₹1842 Cr
Budget left
Spent
₹469 Cr
Remaining
₹1842 Cr
Total
₹2311 Cr
20.3%
Utilized
Original Cost
₹2291 Cr
Revised Cost
₹2311 Cr
Increase
+₹20 Cr
Escalation
+0.9%
Project Approved
Construction / Implementation
Original End Date
2013-11-25
Revised Completion
2026-06-30
Completed
Cost has increased by ₹20 Cr (0.9%) from the original estimate of ₹2291 Cr.
Expenditure stands at ₹469 Cr, which is 20.3% of the revised project cost.
Remaining budget: ₹1842 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.