Original Cost
₹678 Cr
Baseline estimate
Revised Cost
₹1732 Cr
Latest approved cost
Expenditure
₹1140 Cr
Spent to date
Utilization
65.8%
Of revised budget
Cost Status
+155.5%
+₹1054 Cr increase
Remaining
₹592 Cr
Budget left
Spent
₹1140 Cr
Remaining
₹592 Cr
Total
₹1732 Cr
Original Cost
₹678 Cr
Revised Cost
₹1732 Cr
Increase
+₹1054 Cr
Escalation
+155.5%
Project Approved
Construction / Implementation
Original End Date
25/02/2017
Revised Completion
30/09/2026
Completed
Cost has increased by ₹1054 Cr (155.5%) from the original estimate of ₹678 Cr.
Expenditure stands at ₹1140 Cr, which is 65.8% of the revised project cost.
Remaining budget: ₹592 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Energy Storage. Ministry: Ministry of Petroleum & Natural Gas.