Melur - Pilayarpatti - Karaikudi from km 99.920 of NH 38 to km 12.9 of NH 383 Ext.
Original Cost
₹1104 Cr
Baseline estimate
Revised Cost
₹1085 Cr
Latest approved cost
Expenditure
₹948 Cr
Spent to date
Utilization
87.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹137 Cr
Budget left
Budget Utilization
87.4%Spent
₹948 Cr
Remaining
₹137 Cr
Total
₹1085 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
15/03/2022
Revised Completion
15/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1104 Cr — no cost escalation recorded.
Expenditure stands at ₹948 Cr, which is 87.4% of the revised project cost.
Remaining budget: ₹137 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Melur - Pilayarpatti - Karaikudi from km 99.920 of NH 38 to km 12.9 of NH 383 Ext. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1104.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Melur - Pilayarpatti - Karaikudi from km 99.920 of NH 38 to km 12.9 of NH 383 Ex"?
- Melur - Pilayarpatti - Karaikudi from km 99.920 of NH 38 to km 12.9 of NH 383 Ext. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹1104 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1104 Cr and has been revised to ₹1085 Cr — a cost overrun of -1.7%. Expenditure to date: ₹948 Cr (87.4% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Melur - Pilayarpatti - Karaikudi from km 99.920 of NH 38 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618756. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Melur - Pilayarpatti - Karaikudi from km 99.920 of NH 38 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.