II
Original Cost
₹1028 Cr
Baseline estimate
Revised Cost
₹1244 Cr
Latest approved cost
Expenditure
₹832 Cr
Spent to date
Utilization
66.9%
Of revised cost
Cost Overrun
+21.0%
+₹216 Cr
Remaining
₹412 Cr
Budget left
Spent
₹832 Cr
Remaining
₹412 Cr
Total
₹1244 Cr
66.9%
Utilized
Original Cost
₹1028 Cr
Revised Cost
₹1244 Cr
Increase
+₹216 Cr
Escalation
+21.0%
Project Approved
Construction / Implementation
Original End Date
2020-12-11
Revised Completion
2026-09-30
Completed
Cost has increased by ₹216 Cr (21.0%) from the original estimate of ₹1028 Cr.
Expenditure stands at ₹832 Cr, which is 66.9% of the revised project cost.
Remaining budget: ₹412 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.