Original Cost
₹1116 Cr
Baseline estimate
Revised Cost
₹1464 Cr
Latest approved cost
Expenditure
₹588 Cr
Spent to date
Utilization
40.2%
Of revised budget
Cost Status
+31.2%
+₹348 Cr increase
Remaining
₹876 Cr
Budget left
Spent
₹588 Cr
Remaining
₹876 Cr
Total
₹1464 Cr
Original Cost
₹1116 Cr
Revised Cost
₹1464 Cr
Increase
+₹348 Cr
Escalation
+31.2%
Project Approved
Construction / Implementation
Original End Date
05/12/2025
Revised Completion
31/03/2027
Completed
Cost has increased by ₹348 Cr (31.2%) from the original estimate of ₹1116 Cr.
Expenditure stands at ₹588 Cr, which is 40.2% of the revised project cost.
Remaining budget: ₹876 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.