Original Cost
₹1361 Cr
Baseline estimate
Revised Cost
₹1478 Cr
Latest approved cost
Expenditure
₹561 Cr
Spent to date
Utilization
37.9%
Of revised budget
Cost Status
+8.6%
+₹117 Cr increase
Remaining
₹917 Cr
Budget left
Spent
₹561 Cr
Remaining
₹917 Cr
Total
₹1478 Cr
Original Cost
₹1361 Cr
Revised Cost
₹1478 Cr
Increase
+₹117 Cr
Escalation
+8.6%
Project Approved
Construction / Implementation
Original End Date
10/05/2024
Revised Completion
31/01/2027
Completed
Cost has increased by ₹117 Cr (8.6%) from the original estimate of ₹1361 Cr.
Expenditure stands at ₹561 Cr, which is 37.9% of the revised project cost.
Remaining budget: ₹917 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.