Oil & GasIPM · Central Project +28.4% overrun#616933

Lube Modernization & Bottom Upgradation Project at Mumbai Refinery

Ministry of Petroleum & Natural GasMaharashtra
Revised Cost: ₹6008 CrUtilization: 5.4%Overrun: +₹1329 Cr

Original Cost

₹4679 Cr

Baseline estimate

+28% overrun

Revised Cost

₹6008 Cr

Latest approved cost

Expenditure

₹326 Cr

Spent to date

Utilization

5.4%

Of revised budget

Escalated

Cost Status

+28.4%

+₹1329 Cr increase

Remaining

₹5682 Cr

Budget left

Budget Utilization

5.4%
0%25%50%75%100%

Spent

₹326 Cr

Remaining

₹5682 Cr

Total

₹6008 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹4679 Cr

Revised Cost

₹6008 Cr

Increase

+₹1329 Cr

Escalation

+28.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

16/03/2028

Revised Completion

31/08/2029

Completed

Project Details

Project Code616933
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹4679 Cr
Revised Cost₹6008 Cr
Expenditure₹326 Cr
Original End Date16/03/2028
Revised Date31/08/2029

Project Intelligence

Cost has increased by ₹1329 Cr (28.4%) from the original estimate of ₹4679 Cr.

Expenditure stands at ₹326 Cr, which is 5.4% of the revised project cost.

Remaining budget: ₹5682 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Lube Modernization & Bottom Upgradation Project at Mumbai Refinery is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹4679.00 Cr, later revised to ₹6008.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Lube Modernization & Bottom Upgradation Project at Mumbai Refinery"?
Lube Modernization & Bottom Upgradation Project at Mumbai Refinery is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Maharashtra. Original cost: ₹4679 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹4679 Cr and has been revised to ₹6008 Cr — a cost overrun of +28.4%. Expenditure to date: ₹326 Cr (5.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Lube Modernization & Bottom Upgradation Project at Mumbai Re is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 616933. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Lube Modernization & Bottom Upgradation Project at Mumbai Re is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.