Roads & HighwaysIPM · Central Project#618331

lmprovement to 4-Lane with Paved Shoulder from existing km 260000 Design Ch.4560 km to existing km Ch.233000 D. Ch.24560 of Silchar near Nutan Dayapur village - Budha Nagar Section Length-20.00 Km of NH-37 under Package Silchar-Jiribam Pkg-1 in the state of Assam on HAM Mode

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹958 CrUtilization: 22.4%

Original Cost

₹958 Cr

Baseline estimate

On budget

Revised Cost

₹958 Cr

Latest approved cost

Expenditure

₹215 Cr

Spent to date

Utilization

22.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹743 Cr

Budget left

Budget Utilization

22.4%
0%25%50%75%100%

Spent

₹215 Cr

Remaining

₹743 Cr

Total

₹958 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/01/2028

Revised Completion

15/01/2028

Completed

Project Details

Project Code618331
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹958 Cr
Revised Cost₹958 Cr
Expenditure₹215 Cr
Original End Date15/01/2028
Revised Date15/01/2028

Project Intelligence

Project is within original budget of ₹958 Cr — no cost escalation recorded.

Expenditure stands at ₹215 Cr, which is 22.4% of the revised project cost.

Remaining budget: ₹743 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

lmprovement to 4-Lane with Paved Shoulder from existing km 260000 Design Ch.4560 km to existing km Ch.233000 D. Ch.24560 of Silchar near Nutan Dayapur village - Budha Nagar Section Length-20.00 Km of NH-37 under Package Silchar-Jiribam Pkg-1 in the state of Assam on HAM Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹958.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "lmprovement to 4-Lane with Paved Shoulder from existing km 260000 Design Ch.4560"?
lmprovement to 4-Lane with Paved Shoulder from existing km 260000 Design Ch.4560 km to existing km Ch.233000 D. Ch.24560 of Silchar near Nutan Dayapur village - Budha Nagar Section Length-20.00 Km of NH-37 under Package Silchar-Jiribam Pkg-1 in the state of Assam on HAM Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹958 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹958 Cr has not been significantly revised. Expenditure: ₹215 Cr (22.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
lmprovement to 4-Lane with Paved Shoulder from existing km 2 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618331. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. lmprovement to 4-Lane with Paved Shoulder from existing km 2 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.