Original Cost
₹958 Cr
Baseline estimate
Revised Cost
₹958 Cr
Latest approved cost
Expenditure
₹150 Cr
Spent to date
Utilization
15.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹808 Cr
Budget left
Spent
₹150 Cr
Remaining
₹808 Cr
Total
₹958 Cr
Project Approved
Construction / Implementation
Original End Date
15/01/2028
Revised Completion
15/01/2028
Completed
Project is within original budget of ₹958 Cr — no cost escalation recorded.
Expenditure stands at ₹150 Cr, which is 15.6% of the revised project cost.
Remaining budget: ₹808 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.