Original Cost
₹205 Cr
Baseline estimate
Revised Cost
₹205 Cr
Latest approved cost
Expenditure
₹101 Cr
Spent to date
Utilization
49.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹104 Cr
Budget left
Spent
₹101 Cr
Remaining
₹104 Cr
Total
₹205 Cr
Project Approved
Construction / Implementation
Original End Date
21/09/2025
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹205 Cr — no cost escalation recorded.
Expenditure stands at ₹101 Cr, which is 49.4% of the revised project cost.
Remaining budget: ₹104 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.