Landslide treatment work on NH 58 from Kodiyala Km. 266.130 to Devprayag Km. 296.925 10 location under EPC mode in the State of Uttarakhand on EPC Mode
Original Cost
₹193 Cr
Baseline estimate
Revised Cost
₹193 Cr
Latest approved cost
Expenditure
₹98 Cr
Spent to date
Utilization
50.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹95 Cr
Budget left
Budget Utilization
50.7%Spent
₹98 Cr
Remaining
₹95 Cr
Total
₹193 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
11/02/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹193 Cr — no cost escalation recorded.
Expenditure stands at ₹98 Cr, which is 50.7% of the revised project cost.
Remaining budget: ₹95 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Landslide treatment work on NH 58 from Kodiyala Km. 266.130 to Devprayag Km. 296.925 10 location under EPC mode in the State of Uttarakhand on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹193.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Landslide treatment work on NH 58 from Kodiyala Km. 266.130 to Devprayag Km. 296"?
- Landslide treatment work on NH 58 from Kodiyala Km. 266.130 to Devprayag Km. 296.925 10 location under EPC mode in the State of Uttarakhand on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹193 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹193 Cr has not been significantly revised. Expenditure: ₹98 Cr (50.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Landslide treatment work on NH 58 from Kodiyala Km. 266.130 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617888. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Landslide treatment work on NH 58 from Kodiyala Km. 266.130 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.