Original Cost
₹1425 Cr
Baseline estimate
Revised Cost
₹2139 Cr
Latest approved cost
Expenditure
₹1049 Cr
Spent to date
Utilization
49.0%
Of revised budget
Cost Status
+50.1%
+₹714 Cr increase
Remaining
₹1090 Cr
Budget left
Spent
₹1049 Cr
Remaining
₹1090 Cr
Total
₹2139 Cr
Original Cost
₹1425 Cr
Revised Cost
₹2139 Cr
Increase
+₹714 Cr
Escalation
+50.1%
Project Approved
Construction / Implementation
Original End Date
21/02/2023
Revised Completion
30/06/2026
Completed
Cost has increased by ₹714 Cr (50.1%) from the original estimate of ₹1425 Cr.
Expenditure stands at ₹1049 Cr, which is 49.0% of the revised project cost.
Remaining budget: ₹1090 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.